The cooling system of Acciona’s Madrid data center consumes nearly 70% less energy

Acciona’s Data Center Upgrade Cuts Cooling Energy Consumption by Nearly 70%

Acciona, the Spanish infrastructure and renewable energy group, has significantly upgraded the cooling system at its Madrid data center during a routine maintenance visit that revealed its aging components. Operating in over sixty-five countries, the company achieved an impressive reduction of nearly 70% in electricity consumption for the cooling subsystem, which was previously consuming around 2,000 megawatt-hours annually. The engineering team estimates that the return on investment (ROI) for this initiative will be between three to three and a half years.

Cooling systems represent the second-largest source of electricity consumption in data centers, typically accounting for 30% to 40% of total energy use, following server power. European directives (including the revised energy efficiency guidelines issued in 2023, and upcoming data center reporting requirements expected in 2024) along with a French regulation set to take effect in early 2025, are steering operators towards optimization strategies that can provide significant economic benefits. Consequently, programs replacing fixed-speed fans with electronically commutated motors have surged in response to aging equipment installed in the early 2010s.

The backdrop is characterized by a rapidly evolving thermal service market influenced by the dual pressures of rising energy costs and environmental reporting obligations (such as CSRD and European taxonomy). Companies like Vertiv, Schneider Electric, ABB, and Siemens are positioning themselves to modernize existing installations while also designing new high-density sites to accommodate artificial intelligence workloads. Acciona’s case falls under the first category, focusing on optimizing existing facilities through a multi-year maintenance contract with Vertiv.

Lifespan Exceeded During Maintenance Check

The Madrid data center is crucial for Acciona, supporting real-time monitoring, operations management, and coordination of the company’s global asset portfolio. The existing cooling system relied on Vertiv Liebert HPM chillers, which used fixed-speed AC fans. At the time of diagnosis, most of these units were twelve years old and consuming approximately 2,000 megawatt-hours each year, with no capability for adjusting to fluctuating computing loads.

During a routine maintenance visit, a Vertiv service engineer identified the wear on the fans. Analysis indicated that replacing them with variable-speed electronically commutated fans would yield significant efficiency gains. Rather than proceeding with a full overhaul, Acciona and Vertiv opted for a pilot project involving two units to measure actual savings before deciding on a broader rollout. The pilot results confirmed the expected efficiencies, leading to the decision to extend the upgrades across the entire system.

Gradual Replacement Without Interruption

The upgrade involved multiple Liebert HPM chillers of varying capacities, each retrofitted with a variable-speed electronically commutated fan kit. This new system adjusts fan power according to actual demand rather than operating at a constant speed. Additionally, Liebert’s iCOM control system was installed alongside the upgrades to finely regulate fan speeds and coordinate unit operations. The software layer continuously optimizes airflow mapping and intelligently manages thermal load distribution.

The entire process was conducted during business hours without taking the data center offline. The inherent redundancy of the cooling subsystem allowed for the individual shutdown of each unit for replacement, with the remaining equipment handling the thermal load during the intervention. This methodology exemplifies how to modernize operational facilities while maintaining continuous service, a testament to the initial design and maintenance planning that included stringent redundancy.

Three-Year Return on Investment

The measured difference in energy consumption before and after the replacements reached nearly 70%, surpassing initial pilot expectations. Acciona’s engineering leadership estimates the payback period at between three to three and a half years. “We anticipate an ROI period of three to three and a half years,” stated Carlos García Fernández, Acciona’s Director of Engineering and Processes, referring to measurements taken before and after the upgrades. The reduction in energy use results in both operational cost savings and decreased carbon emissions, aligning with the group’s decarbonization goals.

A secondary advantage of the project is the increased capacity available on electrical and thermal lines. With the newly upgraded subsystem consuming significantly less energy, Acciona now has reserve power for future data center expansions without jeopardizing operational stability or resilience. This effect is crucial for technical decision-makers who face challenges in securing additional power supplies from grid operators in saturated metropolitan areas. Therefore, modernization not only serves as a cost-saving measure but also as a proactive strategy for internal self-consumption and delayed investments.

50% to 70% Savings on Ventilation Costs

Acciona’s experience reflects a growing trend among mid-life data centers across Europe, where the replacement of fixed-speed AC fans with variable-speed electronically commutated kits, coupled with precise software control, consistently achieves savings of between 50% and 70% in ventilation costs. This scale of savings is consistent with feedback gathered by industry associations regarding comparable modernization efforts. What sets Acciona apart is the scale of the actual gain (nearly 70%), the transparency of their reported figures, and the clear communication of expected ROI.

For technical leads in France, bound by new reporting obligations under the revised energy efficiency directive and the national regulation effective from 2025, such real-life examples provide measurable insights into achievable savings without the need for architectural overhauls. Future decisions about new facilities intended for artificial intelligence workloads will likely focus on direct liquid cooling and high-density architectures; however, the immediate modernization of existing systems remains the most accessible and well-documented lever for reducing energy consumption in the short term.