Data centers: Île-de-France aims for up to 8 gigawatts by 2040, but electricity limits growth

Electricity access is now a crucial factor in the growth of data centers in the Île-de-France region. The Paris Region Institute predicts that installed power will increase six to eightfold by 2040, driven largely by artificial intelligence. However, connecting a site can take up to nine years in saturated areas, forcing companies housing their information systems in the region to compete for increasingly scarce electrical capacity.

Île-de-France remains the epicenter of French IT hosting, benefiting from millisecond-level latency to the Paris financial district and a stable power network supported by two high-voltage rings. The region accounts for nearly 64% of the installed capacity of data centers in France and continues to expand. The rise of AI is accelerating this trend, and the Paris Region Institute has published a brief report in November 2026 that outlines the electrical implications of this growth.

The Institute’s observatory, which monitors data centers in the region, recorded 151 operational sites in Île-de-France as of January 1, 2026, a significant increase from just a handful two decades ago, with a total installed power of 1.01 gigawatts (GW) in 2025. Their electricity consumption was estimated at 1.7 terawatt-hours (TWh) in 2022, accounting for 3% of regional consumption—a figure that has more than tripled since 2010. The colocation model, where operators rent space to companies for server racks, dominates the market and represents the bulk of ongoing projects in the area.

Anticipating six to eight times the power by 2040

According to the Institute, installed power could reach between 6.5 and 8 GW by 2040, depending on the realization rate of known projects—equivalent to seven to eight nuclear reactors. This conservative estimate does not factor in the densification of existing sites, which would push total capacity even higher. Electricity consumption is projected to follow a similar upward trajectory, reaching approximately 4.5 TWh by 2030 and around 8.2 TWh by 2035.

This growth is primarily driven by equipment density; a colocation rack consumes between 10 to 40 kilowatts depending on its use, while AI infrastructure racks can exceed 100 kilowatts, with dedicated AI racks potentially reaching one megawatt by 2030, nearly equal to an entire data center from the early 2000s. The next major data centers in the region are set to focus on AI; for instance, the AI campus in Fouju, Seine-et-Marne, alone will require 1.4 GW from the grid and plans for nearly 3 GW in backup generators.

Electrical connection as the primary limiting factor

The connection process for data centers depends on the project’s power capacity. Enedis, the distribution network manager, connects sites with capacities under 40 megawatts, while RTE (French National Electricity Transmission Network), which manages the high-voltage grid, connects larger sites. Most historical data centers are linked to the Enedis network, with only six sites totaling 640 megawatts connected through RTE. Newer, more powerful projects are shifting to RTE, where connection timelines in the most congested areas can extend up to nine years. An expedited process can reduce this timeframe to four years for projects exceeding 400 megawatts, under certain conditions.

In these congested zones, connection delays often surpass construction and permitting timelines. The Institute has identified areas at the limit of capacity, such as Plaine Commune and areas near Le Bourget and Charles de Gaulle airports. Efforts are underway to enhance network infrastructure in southern Essonne and the Saclay plateau, while southern Seine-et-Marne is emerging as a new site for development. The average cost of a connection is around 30 million euros, with 30% covered by the tariff for public electricity network usage, which all consumers pay.

The existing queue for connections has faced criticism, as it contains many dormant or incomplete projects, leading to capacity blockages from some operators attempting to outmaneuver their competitors. Since 2024, RTE has tightened requirements for submissions and, beginning in early 2026, has proposed a consultation-based overhaul of the rules on a first-come, first-served basis, prioritizing projects with the most reliable timelines.

Monitoring dormant capacity

On average, data centers in Île-de-France use only 20% to 40% of their connected capacity, according to the Institute. This dormant capacity serves as a buffer for future expansions but also ties up resources that could benefit others. The French Energy Regulatory Commission (CRE) has targeted this issue, with a reform in 2025 allowing recalculation of the power allocated to a client based on their actual consumption five years prior, with a safety margin.

This measure directly impacts data center operators, as a colocation provider that fails to utilize its reserved capacity risks losing it, necessitating better foresight in anticipating promised expansions. Data centers also find themselves competing with industries and heavy transport sectors, which seek out the same industrial wastelands and logistics zones to electrify their operations.

Decade-long planning for hosting in Île-de-France

The report does not undermine the attractiveness of Île-de-France as France’s leading hosting hub. However, it shifts the decision-making horizon, as IT departments looking to expand their hosting capabilities or incorporate AI calculations must reserve their capacity well in advance with an operator whose connected power is already constrained. This capacity must then be explicitly detailed in their contracts.

Companies should engage with their hosting providers regarding connected power, examining both current consumption and the allocation promised for AI clients. The distribution of backup sites also warrants scrutiny, as two Île-de-France sites may be reliant on the same strained network zones. The future growth of data centers in the region will depend more on the electricity the grid can supply than on the availability of real estate.