Vertiv expands its Slovakian factory, but supply chain, connectivity, and construction issues still hinder data centers

Vertiv Expands Slovakian Factory Amid Supply Chain Constraints

During its recent Vertiv Week event, the tech firm Vertiv announced an expansion of its Slovakian manufacturing facility, aimed at speeding up deployment times for data centers. However, the company acknowledges facing challenges related to supply chain disruptions, grid connectivity, and construction timelines.

Vertiv, a provider of power and cooling solutions, highlighted that artificial intelligence (AI) data centers are currently hindered by these obstacles. The delay from site selection to productive operation has become a significant point of differentiation in the market, with both Vertiv and Nvidia tracking the lead time until infrastructure can produce its initial tokens—the basic units of text processed by AI models. This focus on deployment speed was a key theme at Vertiv Week, held in Zagreb from September 21-25. A report by Frost & Sullivan, presented by Vertiv, supports these observations.

On September 28, Vertiv announced the expansion of its site in Nové Mesto nad Váhom, Slovakia, which it touts as its largest manufacturing center in Europe. Over the next 18 to 24 months, the company plans to add approximately 22,000 square meters to the facility, with an anticipated completion between March and September 2028. Vertiv also indicated plans to hire hundreds of employees between 2027 and 2029 to produce power supplies, electrical equipment, and thermal management solutions, including liquid cooling systems. However, specific production capacities and the timeline for the first units have yet to be disclosed.

Supply Chain, Grid Connectivity, and Construction Delays

In its recent announcements, Vertiv identified three primary barriers to progress: supply chain issues, grid connectivity delays, and project execution hurdles. In its July 29 earnings report, the company acknowledged minor schedule setbacks attributed to temporary supply chain congestion and phased project executions, though it did not quantify their impact or specify which components were affected. Additionally, on September 2, Vertiv revealed its acquisition of Utility Innovation Group for approximately $1.45 billion in cash, with up to $1.15 billion contingent on performance targets. This acquisition is presented as a strategic move to enhance quicker access to electricity, thereby reducing reliance on grid connection timelines.

Further strengthening its capabilities, Vertiv announced on September 24 that it had acquired King Environmental Services, a company that prepares, rinses, commissions, and tests liquid cooling circuits in Dublin and Frankfurt. CEO Giordano Albertazzi emphasized that the efficiency of cooling and power supply will depend equally on on-site execution and engineering. Collectively, these developments indicate a shift in bottlenecks, from manufacturing equipment to the availability of energy and on-site construction.

New Manufacturing Capacity by 2028

Earlier in March, we noted that Vertiv was expanding its industrial capabilities in the Americas, particularly with a sevenfold increase in prefabrication capacity in South Carolina. Following this trend, the company has announced hundreds of new hires in Ireland, the acquisition of ThermoKey, and a doubling of production of cooling units at its Tognana facility in Italy, along with over 200 jobs in Croatia and now Slovakia.

However, while the Slovak factory is set to be operational by 2028, it does not alter the timelines for projects currently underway, coinciding with Nvidia’s projections for racks approaching 1 MW. Nvidia’s VP Rod Evans noted in Zagreb that Eastern Europe would help close the gap between U.S. demand and delivered capacities. Though Vertiv has not disclosed its European order volumes, sales in the region fell by 14.8% in the first half of the year, excluding currency effects and acquisitions, indicating that these expansions are a calculated risk based on future demand.

Supplier-Defined Timelines for Token Production

The timing for achieving production readiness continues to depend heavily on supplier capabilities. In a presentation on September 23, Paul Ryan, Vertiv’s EMEA president, identified four key metrics for AI facilities: tokens per second, tokens per watt, lead time to the first token, and tokens per dollar. Vertiv claims it uniquely influences all four metrics. However, there is currently no standard method for clients to compare these indicators across different suppliers. Nvidia’s proprietary NVL72 architecture, developed in conjunction with Vertiv, reportedly allows for a 50% faster deployment, but this is based on projections without detailed methodologies published. Frost & Sullivan commented in its report that clients prefer integrated platforms over standalone products, but did not specify the methodology or sample used.

Vertiv also relies on Nvidia for the qualification of its equipment. On September 21, the company announced that its 2.3 MW CoolChip CDU, a cooling liquid distribution unit, has received “DSX Ready” status—a qualification based on Nvidia’s self-certification program. Scott Armul, Vertiv’s product and technology director, clarified that this qualification does not replace site-specific engineering. For 800V direct current power systems, Nvidia stated on August 11 that the architecture has been developed with Google and Microsoft within the Open Compute Project, with more than 80 manufacturers already building products aligned with this framework. This indicates a clear path for power solutions from chip manufacturers while necessitating customized site solutions for other components.

Support for 2028, but No Guarantees for Ongoing Projects

For CIOs or operators initiating a data center project, this factory expansion will facilitate equipment supply starting in 2028, but it does not assure the timeline for currently active projects. Vertiv has not published its production capacities before or after the expansion, the timeline for the first production runs, or delivery schedules for its equipment, nor have primary sources provided any such information.

Practically, inquiries to the supplier should focus on the agreed-access date for the network at the site, the contractual commissioning schedule, the scope of site-specific engineering remaining for the client despite qualifying for DSX Ready, and the portion of equipment manufactured in Nové Mesto. No release documents clarify which orders this new capacity addresses or whether it precedes European demand.